CONTRACTS
EPC mode of contracting:
Construction of civil works for widening and upgrading of 427.967 kms of roads of Core Road Network (CRN) to two-lane with paved shoulders including maintenance for 5 years have been awarded and works are in progress. Out of 10 contracts, 9 were completed for a length of 392.167Km and under maintenance. EPC 04 work for a length of 35.800Km is nearing completion.
Contract |
SH No. |
Name of the work |
Length in km |
Cost in cores (Rs) |
EPC01 |
SH116 |
Upgrading Kanchipuram –Vandavasi Road Km14/300 to km 36/700 |
22.342 |
184.98 |
SH58 |
Upgrading Sadras - Chengalpattu - Kancheepuram Arakkonam - Thiruthani Road km 0/000 to Km 26/811 |
26.140 |
||
EPC02 |
SH4 |
Upgrading Arcot - Villupuram Road km 29/800 to km110/ 165 and km 113 /325 to km 114/600 |
83.075 |
320.02 |
EPC03 |
SH9 |
Upgrading Cuddalore – Chittoor Road km 41 /700 to km 44/000 and km 45/000 to km 66/190 and construction of a new link road between SH9 and SH 37 (km 66/190 to km 71/147) |
28.450 |
95.22 |
EPC04 |
SH70 |
Upgrading Vridhachalam - Parangipettai Road km 0/000 to km 35/ 800 (Balance Works). EPC-04 |
35.800 |
129.942 |
EPC05 |
SH86 |
Upgrading Omalur - Sankari - Thiruchengode - Paramathy road km 54/800 to km 81/000 |
26.200 |
103.81 |
EPC06 |
SH79 |
Upgrading Malliyakarai -Rasipuram-Trichengode - Erode Road km 0/000 to km 30/600 and km 51/400 to km 71/300 |
50.525 |
224.06 |
EPC07 |
SH95 |
Upgrading Mohanur – Namakkal – Senthamangalam - Rasipuram Road km 0/000 to km 13/385 |
13.385 |
63.95 |
EPC08 |
SH89 |
Upgrading Nanguneri - Bharatavaram - Ovari Road upto ECR junction km 0/000 to km 35/200 |
35.200 |
110.99 |
EPC09 |
SH44 |
Upgrading Paruvakudi - Kovilpatti - Ettayapuram -Vilathikulam - Vembar Road km 22/500 to km 38/750 and km 41/300 to km 56/700 |
31.650 |
152.92 |
EPC10 |
SH41 |
Upgrading Rajapalayam -Sankarankoil-Tirunelveli Road Km 1/800 to km 28/000 and km 33/800 to km 82/800 |
75.200 |
286.50 |
Maintenance through Multi-year Output and Performance Based Road Contract (OPRC)
Roads already upgraded in TNRSP phase 1 have been taken up for maintenance under OPRC mode for a period of 5 years. Under this contract, 2 packages for a total length of 581.493 Km have been taken up for maintenance for a value of Rs.220.07Cr. Works were completed and the roads were handed over to the respective C&M Divisions.
Public Private Partnership (PPP Contract):
PPP 02 work having length of 70.2 Km has been completed and presently it is under 8 year maintenance period.
The packages PPP01 & PPP3 have been converted into EPC16 & EPC 14, EPC 15 respectively and works are under progress.
Additional Works
By utilizing front loaded fund sanctioned by the World Bank and State’s own fund, three additional works EPC-11, EPC-12 and EPC-13 have been taken up and the works are under progress. The details ongoing works are given below:
Package |
Name of the Road |
Length in Km |
Contract Price in Cr |
Status |
EPC 11 |
Four Laning of Omalur to Mecheri Section of SH 222 From Ex.Km 1.150 To Ex.Km 14.300 |
13.170 |
144.64 |
Work is in progress. |
EPC 12 |
Strengthening and Widening of Malliyakarai – Attur roa d of SH-30 (Km.81/125 - 91/200) |
9.884 |
95.14 |
Work is in progress. |
EPC 13 |
Four Laning of Chithode to Erode Section of SH 15 from Existing km 153.500 To Existing Km 161.625 (Design Km 153+600 To Design Km 161+725) |
8.125 |
104.70 |
Work is in progress. |
EPC 14 |
Strengthening and Widening (Four Lane) of Tirunelveli – Sengottai – Kollam Road of SH-39 from Km 5+000 to Km 27+700 (package I) |
22.700 |
176.58 |
Work is in progress. |
EPC 15 |
Strengthening and Widening (Four Lane) of Tirunelveli – Sengottai – Kollam Road (SH 39) Km 27+700 to Km 50+600 (package II) |
22.900 |
254.13 |
Work is in progress. |
EPC16 |
Four Laning of Gobi - Erode Section of SH-15 from Km 123+000 to Km 153+600 |
30.600 |
272.53 |
Work is in progress. |
Tamil Nadu Infrastructure Development Board
An amount of 132.76 Crore has been sanctioned for Preparation of Detailed Project Reports for a length of 3319 Km roads under TNIDB fund. Out of this 3319Km, 1061 Km length of roads have been taken-up in first phase by engaging project preparation consultants in 5 packages.
Institutional Capacity Enhancement (ICE) and Road Safety.
The implementation of ICE and RS components are being taken up through the newly formed ICERS Cell under the control of Director General, Highways Department.