Details of Land Acquisition for TNRSP-II
S. No |
EPC |
Road – Project |
Land Required |
District |
|
Private Land (Sq.mt) |
Govt. Land (Sq.mt) |
||||
1 |
EPC 01 |
Kancheepuram – Vandavasi Road km.14/300- km.6/700 (SH-116) |
14812 |
750 |
Tiruvannamalai, Kancheepuram & Chengalpattu |
2 |
Sadras- Chengalpattu- Kancheepuram- Arakkonam- Thiruthani Road to km.0/000-26/811 (SH-58) |
40874 |
35343 |
||
3 |
EPC-02 |
Arcot- Villupuram road km.29/000- 110/165 & km.113/325-114/600 (SH-04) |
78864 |
4247 |
Tiruvannamalai & Villupuram |
4 |
EPC -03 |
Cuddalore- Chittoor rod km.41/700- 44/000 & km.45/000-66/190 including Thirukkovilur link road km.66/190- 1/147 (SH-09) |
150735 |
9014 |
Villupuram & Kallakuruchi |
5 |
EPC -04 |
Vridhachalam- Parangipettai road km.0/000-35/800 (SH-70) |
49310 |
11136 |
Cuddalore |
6 |
EPC-05 |
Omalur- Sankari- Thiruchengode- Paramathy road km.54/800- 81/000 (SH-86) |
37770 |
4028 |
Namakkal |
7 |
EPC-06 |
Malliyakarai- Rasipuram- Thiruchengode-Erode Road km.0/000-30/600 & km.51/400-71/300 (SH-79) |
81896 |
13505 |
Salem & Namakkal |
8 |
EPC-07 |
Mahanur- Namakkal- Senthamangalam- Rasipuram Road km.0/600- 13/200 & km.15/700-16/200 (SH-95) |
1870 |
1561 |
Namakkal |
9 |
EPC-08 |
Nanguneri- Bharathavaram- Ovari road km.0/000- 35/200 (SH-89) |
164696 |
52007 |
Tirunelveli |
10 |
EPC-09 |
Paravakudi- Kovilpatti- Ettayapuram road km.22/500-38/750 & km.41/300-56/700 (SH-44) |
26070 |
5400 |
Tuticorin, Virudhunagar, Tenkasi |
11 |
EPC-10 |
Rajapalayam- Sankarankoil- Tirunelveli Road km.1/800-28/000 & km.33/800-82/800 (SH-41) |
45858 |
18589 |
Tirunelveli, Tenkasi & Virudhunagar |
12 |
EPC-11 |
Four laning of Omalur to Mecheri Section of SH 222 from existing km.1.150 to existing km.14.300 |
65284 |
9979 |
Salem |
13 |
EPC-12 |
Strengthening and Widening of Malliyakarai- Attur road of SH-30 (km.81/125-91/200) |
22108 |
3201 |
Salem |
14 |
EPC-13 |
Four laning of Chithode to Erode section of SH-15 from existing km.153.500- existing km.161.625 (Design km.153+600 to Design km.161+725) |
11137 |
1523 |
Erode |
15 |
PPP03(EPC14&15) |
Tirunelveli – Senkottai- Kollam km.5/000-50/600 (SH-39) |
201419 |
25651 |
Tirunelveli & Tenkasi |
16 |
PPP 01 (EPC-16) |
Gobi- Erode km.123/000-153/400 (SH-15) |
102102 |
8144 |
Erode |
17 |
PPP 02 |
Oddanchatram- Dharapuram-Tiruppur km.37/400- 126/200 (SH-37) |
717190 |
46354 |
Tiruppur & Dindigul |
Total |
1811995 |
250432 |
LAND ACQUISTION (LA), RESETTLEMENT AND REHABILITATION (R&R) ACTIVITIES
The Resettlement Policy Framework (RPF), prepared in line with the new “Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement-RFCTLARR Act, 2013 and the World Bank’s Operational guidelines have been approved by the Government for giving compensation and resettlement of the Project Affected People.
The Resettlement Policy Framework covers the principles and objectives of
resettlement, process for conducting census survey of Project Affected
People (PAP), Socio-economic Surveys and Preparation of Entitlement Matrix
(EM), Resettlement Action Plan (RAP), is prepared for the Project Roads
based on the approved Entitlement Matrix and following the above, final
awards are passed by the
TNRSP-II.
An extent of 180 Ha of patta lands have been acquired as per the provisions of Tamil Nadu Highways Act-2001 for the Project by paying compensation in line with the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.