Project Brief
TNRSP–II is being executed with World Bank loan assistance of US$300 Million (reimbursed as Rs. 2122.90 Crore) at a total cost of Rs.5171 Crore.
Loan Period
Loan Started on - May 28, 2015
Loan Period ended on – June 30, 2021
EPC mode of contracting :
Construction of civil works for widening and upgrading of 427 kms of roads of Core Road Network (CRN) to two-lane with paved shoulders including maintenance for 5 years have been taken up in 10 packages. Table - 1 shows the details of works taken up under 10 EPC packages.
Table - 1
Contract |
SH No |
Name of the road stretch |
Length in km |
Agreement amount Rs. in Crore |
EPCO1 |
SH116 |
Upgrading Kanchipuram - Vandavasi Road (SH116) Km 14/300 to km 36/700 |
22.342 |
184.98 |
SH58 |
Upgrading Sadras - Chengalpattu - Kancheepuram - Arakkonam - Thiruthani Road (SH58) km 0/000 to km 26/811 |
26.140 |
||
EPC02 |
SH4 |
Upgrading Arcot - Villupuram Road (SH4) km 29/800 to km 110/165 and km 113/325 to km 114/600 |
83.075 |
320.02 |
EPC03 |
SH9 |
Upgrading Cuddalore - Chittoor Road (SH9) km 41/700 to km 44/000 and km 45/000 to km 66/190 and construction of a new link road between SH9 and SH137 (km 66/190 to km 71/147) |
28.450 |
95.22 |
EPC04 |
SH70 |
Upgrading Vridhachalam - Parangipettai Road (SH70) km 0/000 to km 35/800 |
35.800 |
162.41 |
EPC05 |
SH86 |
Upgrading Omalur - Sankari - Thiruchengode - Paramathy road (SH86) km 54/800 to km 81/000 |
26.200 |
103.81 |
EPC06 |
SH79 |
Upgrading Malliyakarai - Rasipuram - Trichengode - Erode Road (SH79) km 0/000 to km 30/600 and km 51/400 to km 71/300 |
50.525 |
224.06 |
EPC07 |
SH95 |
Upgrading Mohanur – Namakkal – Senthamangalam - Rasipuram Road (SH95) km 0/000 to km 13/100 |
13.385 |
63.95 |
EPC08 |
SH89 |
Upgrading Nanguneri - Bharatavaram - Ovari Road (SH89) upto ECR junction km 0/000 to km 35/200 |
35.200 |
110.99 |
EPC09 |
SH44 |
Upgrading Paruvakudi - Kovilpatti - Ettayapuram -Vilathikulam - Vembar Road (SH44) km 22/500 to km 38/750 and km 41/300 to km 56/700 |
31.650 |
152.97 |
EPC1O |
SH41 |
Upgrading Rajapalayam - Sankarankoil - Tirunelveli Road (SH41) km 1/800 to km 28/000 and km 33/800 to km 82/800 |
75.200 |
286.50 |
TOTAL |
427.967 |
1704.91 |
Out of the above 10 packages, 9 packages have been completed except EPC 04 package. EPC 04 balance work is nearing completion.
PPP (Modified Annuity) mode of contracting:
146 Km length of roads are proposed to be widened as four lane thro’ PPP – mode in three packages Out of these 3 packages PPP02 package having length of 70.2Km Four laning of Oddanchatram– Dharapuram–Avinashipalayam Road (SH 37) has been completed and is under 8 years maintenance period.
PPP-01 package (Public Private Partnership-01) has been converted into EPC 16 and PPP-03 package (Public Private Partnership-03) has been converted into two works namely EPC-14, EPC-15 and the works are under progress.
Additional Works
By utilizing front loaded fund sanctioned by the World Bank and State’s own fund, three additional works, EPC-11, EPC-12 and EPC-13 have been taken up and the works are under progress.
List of ongoing Works is tabulated below
Package |
Name of the Road |
Length in Km |
Contract Price in Cr |
Current Status |
Two-lane with paved shoulders |
||||
EPC 12 |
Strengthening and Widening of Malliyakarai – Attur road of SH-30 (Km.81/125 - 91/200) |
9.884 |
95.14 |
Work is in progress. |
Sub Total (A) |
9.884 |
95.14 |
||
Four Lane Road |
||||
EPC 11 |
Four Laning of Omalur to Mecheri Section of SH 222 From Ex.Km 1.150 To Ex.Km 14.300 |
13.170 |
144.64 |
Work is in progress. |
EPC 13 |
Four Laning of Chithode to Erode Section of SH 15 from Existing km 153.500 To Existing Ch 161.625 (Design Ch 153+600 To Design Km 161+725) |
8.125 |
104.70 |
Work is in progress. |
EPC 14 |
Strengthening and Widening (Four Lane) of Tirunelveli – Sengottai – Kollam Road of SH-39 from Km 5+000 to Km 27+700 (package I) |
22.700 |
176.58 |
Work is in progress. |
EPC 15 |
Strengthening and Widening (Four Lane) of Tirunelveli – Sengottai – Kollam Road (SH 39) Km 27+700 to Km 50+600 (package II) |
22.900 |
254.13 |
Work is in progress. |
EPC16 |
Four Laning of Gobi - Erode Section of SH-15 from Km 123+000 to Km 153+600 |
30.600 |
272.53 |
Work is in progress. |
Sub Total (B) |
97.495 |
952.58 |
||
Grand Total (A+B) |
107.379 |
1047.72 |
DPR Preparation by using Tamil Nadu Infrastructure Development Board (TNIDB) Fund:
Preparation of Detailed Project Reports for a length of 3319 Km for an amount of Rs. 132.76 Cr has been sanctioned under TNIDB fund. In the first phase, 1061 Km length of roads have been taken up in 5 packages namely PPC 06 to PPC 10 and the DPR works are in progress.
Institutional Capacity Enhancement and Road Safety (ICERS)
Institutional Capacity Enhancement and Road Safety works are taken up at a cost of Rs.66.00 Crore and Rs.120.00 Crore respectively under World Bank Funded TNRSP II.